A 686,000 ft2 office/warehouse was under construction for Sunrider International in Midlothian, TX. The building consisted of 9 ¼” thick tilt wall panels and steel columns supported on 24” diameter under reamed concrete piers. Soon after the panels were set into place, the panels began to settle. Some of the panels settled as much as 5-inches before the roof had even been installed. Sunrider hired a new construction team to determine the cause of the settlement and to provide the most cost-effective solution. James F. Turner Engineers and Alpha Testing became the new Structural and Geotechnical EOR’s for the project. It was quickly determined that some of the existing concrete piers were under designed to support the structural loads of most of the tilt wall panels and the mezzanine. Alpha Testing had worked with Ram Jack and Fortified Engineering Solutions on a similar project so recommended them on this one.
With the structural loads and soil borings being provided by the EOR’s, Fortified Engineering Solutions designed 3 ½” diameter driven piles to raise the tilt wall panels to their proper elevation and prevent any future settlement. James F. Turner Engineers and Alpha Testing also preformed an analysis on the concrete piers supporting the mezzanine columns and found them to be under designed as well. Fortified Engineering Solutions designed 3 ½” diameter new construction helical piles to support the excess mezzanine load that exceeded the capacity of the existing concrete piers.
Tilt Wall Panels:
Mezzanine:
Ram Jack with the team described above kept the project moving forward to avoid additional delays and allow other trades to keep on schedule. This was very important as Sunrider was in the process of relocating their current manufacturing facility from California to Texas.